Loop 1604 North Expansion Status, Cost & Completion Date (2026 Guide)
The Loop 1604 North Expansion is a major infrastructure project expanding 23 mi of San Antonio's northern corridor from SH 16 to I-35 under the official loop 1604 north expansion program. Managed by TxDOT, this $1.4B urban highway upgrade replaces a congested four-lane roadway with a modern ten-lane expressway featuring expanded frontage roads and multi-use paths. Funded through TxDOT State and Federal Transportation Improvement Programs, the expansion addresses heavy freight and commuter traffic across Bexar County's fastest-growing commercial districts. The official plans and route map outline an alignment built in five distinct construction segments to minimize traffic disruption while right-of-way acquisition and utility relocations proceed. Following extensive environmental review processes, the project enhances regional connectivity near I-10 and US 281. Construction activities remain actively underway, with full completion date milestones targeted for 2028, significantly reducing travel times across Northern San Antonio.
Project information is compiled from official agency documents, federal records, environmental reviews, and verified public announcements.
Want Your Brand Featured Here?
Reach thousands of decision-makers and investors searching for infrastructure projects every month.
Loop 1604 North Expansion Route Map & Alignment
View and download the latest Loop 1604 North Expansion route map showing the project alignment, major junctions, regions covered and connectivity corridors.
Statewide Network System Phases
| Phase | Route Alignment | Length | Current Status |
|---|---|---|---|
| Segment 1 | SH 16 (Bandera Rd) to I-10 | 4.5 miles | Under Construction |
| Segment 2 | I-10 Interchange | 2 miles | Under Construction |
| Segment 3 | I-10 to US 281 | 4.5 miles | Under Construction |
| Segment 4 | US 281 to Redland Rd | 4 miles | Under Construction |
| Segment 5 | Redland Rd to I-35 | 8 miles | Final Design / Early Works |
Active Construction Packages
| Package | Section Covered | Contractor | Progress / Status |
|---|---|---|---|
| SEG-1 | SH 16 to I-10 | Williams Brothers Construction Co. | Active Construction |
| SEG-2 | I-10 Interchange Flyovers | Lane Construction Corporation | Active Construction |
| SEG-3 | I-10 to US 281 | Capital Excavation | Active Construction |
Key Engineering Structures & Viaducts
I-10 / Loop 1604 Direct Connector Interchange
Five-level direct connector interchange replacing the existing cloverleaf configuration to eliminate dangerous weave movements.
US 281 Flyover Connectors
Elevated direct connectors designed to streamline high-volume commuter transfers between key northern arterials.
Key Project Milestones Timeline
Groundbreaking
Construction officially began on Segment 1 from SH 16 to I-10.
Interchange Work Commences
TxDOT initiated major construction on the multi-level I-10 interchange.
Flyover Steel Erection
Crews placed steel support girders for direct connector bridges at I-10.
Target Completion
Projected final completion date across all five construction segments.
Latest Project Developments
The Loop 1604 North Expansion construction and engineering execution continue to progress across monitored project packages under the direction of TxDOT.
Civil contractors and agency engineers are executing earthworks, structural deck installations, utility relocations, and system integration testing to ensure adherence to safety and operational schedules.
Loop 1604 North Expansionโ Cost โข Route โข Timeline
| Parameter | Technical Details |
|---|---|
| Project Name | Loop 1604 North Expansion |
| Country / Geography | USA |
| Region / Corridor | Texas |
| Executing Agency | TxDOT |
| Route Designation | Loop 1604 |
| Funding Model | TxDOT Unified Transportation Program (State & Federal Highway Funds) |
| Project Type | Interstate Beltway / Highway Expansion |
| Total Length | 23 miles |
| Estimated Cost | $1.4B |
| Land Acquisition (%) | 95% |
| Construction Progress (%) | 55% |
| Expected Completion | 2028 |
Impact Zone: Affected Settlements
Places, towns, and villages located within the 1.5 km and 500m buffer corridors, as well as road crossing nodes along the project's alignment, identified via OpenStreetMap spatial analysis.
Running GIS Spatial Analysis...
Latest Loop 1604 North Expansion News & Developments (2026)
News Timeline (0 Articles)
Loop 1604 North Expansion Video Updates
Frequently Asked Questions (FAQ)
The Loop 1604 North Expansion is a major infrastructure project in the United States, forming part of the national infrastructure development program.
The Loop 1604 North Expansion is considered critical infrastructure for improving regional connectivity, reducing travel times, and supporting economic growth in the project corridor.
The target completion date for the Loop 1604 North Expansion is 2028. Completion may occur in phases as individual sections are finalized.
The estimated project cost for the Loop 1604 North Expansion is $1.4B. Cost figures are subject to revision based on scope adjustments and procurement outcomes.
Funding for the Loop 1604 North Expansion comes from a combination of federal government allocations, state contributions, and where applicable, public-private partnership arrangements. Specific funding breakdowns are disclosed in official project documentation.
The Loop 1604 North Expansion is implemented by TxDOT. Project oversight, funding disbursement, and construction monitoring are shared across these agencies.
The current status of the Loop 1604 North Expansion is: Under Construction. Construction progress and key milestones are tracked and updated regularly on this page.
The most recent developments for the Loop 1604 North Expansion are listed in the Latest Developments section on this page. Information is compiled from official agency announcements and verified public records.
The Loop 1604 North Expansion spans approximately 23 miles.
Related Infrastructure Projects
Hudson Tunnel Project
Under ConstructionNew York Penn Station โ Secaucus Junction (NJ)
Gateway Program
Under DevelopmentNew York Penn Station โ Newark, NJ
Purple Line (Maryland)
Under ConstructionBethesda, MD โ New Carrollton, MD
Stay Updated on U.S. Infrastructure Projects
Get the latest updates on rail, highway, tunnel, bridge, and airport projects across the United States.