Loop 1604 North Expansion Status, Cost & Completion Date (2026 Guide)

Last Updated: 1 October 2026

The Loop 1604 North Expansion is a major infrastructure project expanding 23 mi of San Antonio's northern corridor from SH 16 to I-35 under the official loop 1604 north expansion program. Managed by TxDOT, this $1.4B urban highway upgrade replaces a congested four-lane roadway with a modern ten-lane expressway featuring expanded frontage roads and multi-use paths. Funded through TxDOT State and Federal Transportation Improvement Programs, the expansion addresses heavy freight and commuter traffic across Bexar County's fastest-growing commercial districts. The official plans and route map outline an alignment built in five distinct construction segments to minimize traffic disruption while right-of-way acquisition and utility relocations proceed. Following extensive environmental review processes, the project enhances regional connectivity near I-10 and US 281. Construction activities remain actively underway, with full completion date milestones targeted for 2028, significantly reducing travel times across Northern San Antonio.

Project information is compiled from official agency documents, federal records, environmental reviews, and verified public announcements.

FEATURED PARTNER
ADVERTISEMENT

Want Your Brand Featured Here?

Reach thousands of decision-makers and investors searching for infrastructure projects every month.

YOUR BRAND HEREPrime Infrastructure Placement
Total Length23 miles
Estimated Cost$1.4B
Implementing AgencyTxDOT
Current StatusUnder Construction
Completion Target2028
Route Map

Loop 1604 North Expansion Route Map & Alignment

View and download the latest Loop 1604 North Expansion route map showing the project alignment, major junctions, regions covered and connectivity corridors.

Loading GIS Map Environment...
Project Info๐Ÿ“ Loop 1604 North Expansion
Total Length23 miles
Estimated Cost$1.4B
Current StatusUnder Construction

Statewide Network System Phases

PhaseRoute AlignmentLengthCurrent Status
Segment 1SH 16 (Bandera Rd) to I-104.5 milesUnder Construction
Segment 2I-10 Interchange2 milesUnder Construction
Segment 3I-10 to US 2814.5 milesUnder Construction
Segment 4US 281 to Redland Rd4 milesUnder Construction
Segment 5Redland Rd to I-358 milesFinal Design / Early Works

Active Construction Packages

PackageSection CoveredContractorProgress / Status
SEG-1SH 16 to I-10Williams Brothers Construction Co.Active Construction
SEG-2I-10 Interchange FlyoversLane Construction CorporationActive Construction
SEG-3I-10 to US 281Capital ExcavationActive Construction

Key Engineering Structures & Viaducts

Interstate 10 and Loop 1604 Junction

I-10 / Loop 1604 Direct Connector Interchange

Five-level direct connector interchange replacing the existing cloverleaf configuration to eliminate dangerous weave movements.

US 281 and Loop 1604 Interchange

US 281 Flyover Connectors

Elevated direct connectors designed to streamline high-volume commuter transfers between key northern arterials.

Key Project Milestones Timeline

2021

Groundbreaking

Construction officially began on Segment 1 from SH 16 to I-10.

2022

Interchange Work Commences

TxDOT initiated major construction on the multi-level I-10 interchange.

2024

Flyover Steel Erection

Crews placed steel support girders for direct connector bridges at I-10.

2028

Target Completion

Projected final completion date across all five construction segments.

Latest Project Developments

The Loop 1604 North Expansion construction and engineering execution continue to progress across monitored project packages under the direction of TxDOT.

Civil contractors and agency engineers are executing earthworks, structural deck installations, utility relocations, and system integration testing to ensure adherence to safety and operational schedules.

Technical Specifications

Loop 1604 North Expansionโ€“ Cost โ€ข Route โ€ข Timeline

ParameterTechnical Details
Project NameLoop 1604 North Expansion
Country / GeographyUSA
Region / CorridorTexas
Executing AgencyTxDOT
Route DesignationLoop 1604
Funding ModelTxDOT Unified Transportation Program (State & Federal Highway Funds)
Project TypeInterstate Beltway / Highway Expansion
Total Length23 miles
Estimated Cost$1.4B
Land Acquisition (%)95%
Construction Progress (%)55%
Expected Completion2028
GIS Corridor Analysis

Impact Zone: Affected Settlements

Places, towns, and villages located within the 1.5 km and 500m buffer corridors, as well as road crossing nodes along the project's alignment, identified via OpenStreetMap spatial analysis.

Running GIS Spatial Analysis...

Timeline

Latest Loop 1604 North Expansion News & Developments (2026)

Verified project updates from news sources and official announcements

News Timeline (0 Articles)

Video Coverage

Loop 1604 North Expansion Video Updates

Latest drone footage, progress reports, and ground coverage
Q&A

Frequently Asked Questions (FAQ)

Explore More Projects

Related Infrastructure Projects

Last updated: June 2026 ยท Source: USDOT, FTA, State DOT project dataโ† BACK TO HOME

Stay Updated on U.S. Infrastructure Projects

Get the latest updates on rail, highway, tunnel, bridge, and airport projects across the United States.

โœ“Project milestones
โœ“Government approvals
โœ“Construction progress
โœ“New project launches
Never miss a project update.

Join the Infracapitalist Newsletter