Maryland Purple Line: 2026 Status, Cost, Timeline & Route Map

Last Updated: 1 October 2026

The Maryland Purple Line project, officially recognized as the maryland purple line, is a 16.2 mi light rail transit line extending from Bethesda to New Carrollton. Managed by MDOT and MTA with USDOT and FTA federal oversight, the line utilizes a public-private partnership (P3) funding model to build a major east-west transit arterial across Montgomery and Prince George's counties. The 21-station alignment operates along a dedicated right-of-way, directly connecting WMATA Metrorail, MARC, and Amtrak service centers. Grounded in a comprehensive environmental review and official plans, the project replaces congested roadway reliance with sustainable transit capacity. Urban planners engineered the route map to leverage existing brownfield corridors, creating vital transit-oriented development hubs near key university and commercial districts. As crews advance toward the target completion date, the corridor delivers transformative transit connectivity, economic renewal, and cross-county integration for thousands of daily suburban commuters.

Project information is compiled from official agency documents, federal records, environmental reviews, and verified public announcements.

FEATURED PARTNER
ADVERTISEMENT

Want Your Brand Featured Here?

Reach thousands of decision-makers and investors searching for infrastructure projects every month.

YOUR BRAND HEREPrime Infrastructure Placement
Total Length16.2 miles
Estimated Cost$9.8B
Implementing AgencyMTA
Current StatusUnder Construction
Completion Target2027
Route Map

Maryland Purple Line Route Map & Alignment

View and download the latest Maryland Purple Line route map showing the project alignment, major junctions, regions covered and connectivity corridors.

Loading GIS Map Environment...
Project Info📍 Maryland Purple Line
Total Length16.2 miles
Estimated Cost$9.8B
Current StatusUnder Construction

Statewide Network System Phases

PhaseRoute AlignmentLengthCurrent Status
Full Corridor ConstructionBethesda to New Carrollton16.2 milesUnder Construction

Active Construction Packages

PackageSection CoveredContractorProgress / Status
P3-DBMain Line Design-Build ContractMTSJ (Maryland Transit Solutions)Active

Major Stations & Multi-Modal Interchanges

Bethesda

Bethesda

Under Construction

Interchange: WMATA Red Line

Silver Spring

Silver Spring Transit Center

Under Construction

Interchange: WMATA Red Line, MARC

College Park

College Park - UMD

Under Construction

Interchange: WMATA Green Line, MARC

New Carrollton

New Carrollton

Under Construction

Interchange: WMATA Orange Line, MARC, Amtrak

Key Engineering Structures & Viaducts

Bethesda

Bethesda Shaft and Tunnel

Deep vertical elevator shaft connecting underground Metrorail Red Line platform to surface LRT station.

Silver Spring

Capital Crescent Trail Structure

Grade-separated multi-use bridge structure carrying light rail tracks parallel to pedestrian bicycle paths.

Key Project Milestones Timeline

2014

Record of Decision Issued

FTA issued the official Record of Decision approving environmental clearance for the transit corridor.

2016

P3 Concession Agreement Executed

MDOT MTA executed a long-term public-private partnership agreement for project delivery.

2022

Design-Build Contractor Replacement

Maryland Transit Solutions assumed design-build construction duties under a revised $3.4B contract.

2024

Corridor Rail Installation

Crews laid continuous track across key alignments in Prince George's and Montgomery counties.

Latest Project Developments

The Maryland Purple Line construction and engineering execution continue to progress across monitored project packages under the direction of MTA.

Civil contractors and agency engineers are executing earthworks, structural deck installations, utility relocations, and system integration testing to ensure adherence to safety and operational schedules.

Technical Specifications

Maryland Purple Line– Cost • Route • Timeline

ParameterTechnical Details
Project NameMaryland Purple Line
Country / GeographyUSA
Region / CorridorMid-Atlantic
Executing AgencyMTA
Route DesignationMD-193 Corridor
Funding ModelP3 / Public-Private Partnership
Project TypeLight Rail
Total Length16.2 miles
Estimated Cost$9.8B
Land Acquisition (%)100%
Construction Progress (%)70%
Expected Completion2027
GIS Corridor Analysis

Impact Zone: Affected Settlements

Places, towns, and villages located within the 1.5 km and 500m buffer corridors, as well as road crossing nodes along the project's alignment, identified via OpenStreetMap spatial analysis.

Running GIS Spatial Analysis...

Timeline

Latest Maryland Purple Line News & Developments (2026)

Verified project updates from news sources and official announcements

News Timeline (0 Articles)

Video Coverage

Maryland Purple Line Video Updates

Latest drone footage, progress reports, and ground coverage
Q&A

Frequently Asked Questions (FAQ)

Explore More Projects

Related Infrastructure Projects

Last updated: June 2026 · Source: USDOT, FTA, State DOT project data← BACK TO HOME

Stay Updated on U.S. Infrastructure Projects

Get the latest updates on rail, highway, tunnel, bridge, and airport projects across the United States.

✓Project milestones
✓Government approvals
✓Construction progress
✓New project launches
Never miss a project update.

Join the Infracapitalist Newsletter